From Sarah Zeeman <szeeman@gmail.com>
To Linda Abaray <linda.abaray@brookhavenga.gov>
Subject Re: Stop work order - CV21-00377
Date Tue, 22 Mar 2022 08:30:00 -0400
Email Body
Hi Linda,

We've updated the timeline;  is this still correct?

   - 2/4/20 -  #PRR-600-2021 BLR20-00100 Plans Submitted 2.4.2020.pdf  by
   2746 Grove Street *shows a sanitary sewer easement* in the backyard & no
   drainage plans. Link:  <http://goog_1898538480>
   https://prnt.sc/HT24enRVnl57


   - 5/20/20 - COB Variance Hearing - VAR20-00015 Plans submitted by 2746
   Grove Street* with no sanitary sewer easement visible* in the back yard
   & no drainage plans. Link: https://prnt.sc/zlOI_XOrPr56    COB approved
   a variance on the DeKalb county sanitary sewer easement.


   - 9/21/21 - Ticket submitted:
   https://brookhavenga.citysourced.com/servicerequests/2289303
   https://prnt.sc/ISMA7t1B0pSE
   - 10/8/21 - Ticket closed
   - 10/8/21 - Stop-work order issued for drainage violation
   - 11/3/21 - Stop-work order listed as closed in the COB case report and
   was released, and the drainage violation was not cured
   - 2/28/22 - Drainage violation was cured enough to comply with COB's
   code for the CO to be issued.


Thank you in advance for your assistance,

Best,
Sarah




On Wed, Mar 16, 2022 at 6:08 PM Linda Abaray <linda.abaray@brookhavenga.gov>
wrote:

> That timeline appears to match what was provided to you in your open
> records request.
>
>
>
> <http://www.brookhavenga.gov/>
>
> *Linda Abaray*
>
> Director of Community Development
>
> City of Brookhaven
>
> *📱* 678-274-2574 |*☎* 404-637-0536
>
> Linda.Abaray@BrookhavenGA.gov
>
> www.BrookhavenGA.gov <http://www.brookhavenga.gov/>
>
> 4362 Peachtree Rd.|Brookhaven, GA|30319
>
>
> ------------------------------
>
> This e-mail message (including any attachments) is for the sole use of the
> intended recipient(s) and may contain confidential and privileged
> information. If you have received this message in error, please contact the
> sender and destroy all copies of the original message (including
> attachments). The City of Brookhaven is a public entity subject to the
> Official Code of Georgia Annotated §§ 50-18-70 to 50-18-76 concerning
> public records.
>
>
>
> *From:* Sarah Zeeman <szeeman@gmail.com>
> *Sent:* Wednesday, March 16, 2022 5:18 PM
> *To:* Linda Abaray <linda.abaray@brookhavenga.gov>
> *Subject:* Re: Stop work order - CV21-00377
>
>
>
> Hi Linda,
>
>
>
> Is this the correct timeline from start to finish?
>
>
>
> For clarification, we included the original ticket in the timeline for
> confirmation.
>
> https://prnt.sc/ISMA7t1B0pSE
>
> · 9/21/21 - Ticket submitted:
> https://brookhavenga.citysourced.com/servicerequests/2289303
>
> · 10/8/21 - Ticket closed
>
> · 10/8/21 - Stop-work order issued for drainage violation
>
> · 11/3/21 - Stop-work order listed as closed in the COB case report and
> was released, and the drainage violation was not cured
>
> · 2/28/22 - Drainage violation was cured enough to comply with COB's code
> for the CO to be issued.
>
>
>
> Thank you in advance for your assistance.
>
>
>
> Best,
>
> Sarah
>
>
>
>
>
> On Wed, Mar 16, 2022 at 4:11 PM Sarah Zeeman <szeeman@gmail.com> wrote:
>
>
>    - 10/8/21 Stop-work order issued for drainage violation
>    - 11/3/21 Stop-work order released, but the  drainage violation was
>    not cured
>    - 2/28/22 Drainage violation was cured enough to be in compliance with
>    COB's code for the CO to be issued.
>
> Is this the correct timeline?
>
>
>
>
>
> On Wed, Mar 16, 2022 at 1:32 PM Linda Abaray <
> linda.abaray@brookhavenga.gov> wrote:
>
> 11/3 was the date the stop work order was release. The certificate of
> occupancy issue date would be the date that the site was in compliance with
> the code.
>
>
>
> <http://www.brookhavenga.gov/>
>
> *Linda Abaray*
>
> Director of Community Development
>
> City of Brookhaven
>
> *📱* 678-274-2574 |*☎* 404-637-0536
>
> Linda.Abaray@BrookhavenGA.gov
>
> www.BrookhavenGA.gov <http://www.brookhavenga.gov/>
>
> 4362 Peachtree Rd.|Brookhaven, GA|30319
>
>
> ------------------------------
>
> This e-mail message (including any attachments) is for the sole use of the
> intended recipient(s) and may contain confidential and privileged
> information. If you have received this message in error, please contact the
> sender and destroy all copies of the original message (including
> attachments). The City of Brookhaven is a public entity subject to the
> Official Code of Georgia Annotated §§ 50-18-70 to 50-18-76 concerning
> public records.
>
>
>
> *From:* Sarah Zeeman <szeeman@gmail.com>
> *Sent:* Tuesday, March 15, 2022 1:21 PM
> *To:* Linda Abaray <linda.abaray@brookhavenga.gov>
> *Subject:* Stop work order - CV21-00377
>
>
>
> Hi Linda,
>
>
>
> As you mentioned to direct all questions to you.
>
>
>
> We had questions about the stop-work order from PRR-713-2021.
>
> We're looking for the final day that the drainage Stop-work order was
> lifted.
>
>
>
> From the ORR - A stop-work order for the drainage was issued on 10/8, and
> the code enforcement case report records were closed on 11/3.
>
>
>
> Is 11/3 the correct date Brookhaven 