Email

Header Value
From Vincent Lim <vincent@haight-davis.com>
To Sarah Zeeman <szeeman@gmail.com>
CC Frank Davis <frank@haight-davis.com>, Lisa Nelson <lisa@haight-davis.com>
Subject Re: Background Information
Date Mon, 02 May 2022 16:02:21 -0400
Email Body
Ms Zeeman,

Could you please send over the photos of the asphalt over. Additionally,
what is the name of the document/survey with the setbacks measurements for
your property/ if you have not sent it over yet, please do.

Vincent Lim, Project Engineer
Haight Davis & Associates, Inc.
1480 Tarver Road
Davisboro, GA 31018
Tel:  770-979-6650
www.haight-davis.com

*PLEASE NOTE CHANGE OF ADDRESS*


On Fri, Apr 29, 2022 at 1:29 PM Sarah Zeeman <szeeman@gmail.com> wrote:

>
> COB
>
>    - 6.15.17 COB Began Prepping  area for the stormwater project on my
>    corner
>    - 6.24.17 Began scraping Osborne rd asphalt and removed my tree and
>    corner bush
>    - 7.2.17 COB Broke ground
>    - 8.17.17 Buried street asphalt in the yard and covered with hay
>    - 8.22.18 email attached - Response to my complaints after 430 days of
>    the initial concerns/emails etc
>    - 10.3.18  Buried topsoil incorrectly
>    - https://brookhavenga.citysourced.com/servicerequests/2499482
>    - 2.9.22 Email attached COB told me it was my responsibility to fix
>    their mishandlings on the corner
>
>
> ATT
>
>    - 8/8/18 surveyed/ dug up part of drain area and initial steps in
>    removing the box
>    - 7/17/19 fully removed ATT box
>    - (trying to locate the date) They returned after the complaint to dig
>    up the remaining underground wires ATT tried to abandon
>    - 9/11/19 file date of Record Release
>    - ATT Never fulfilled the stipulation section to repair the fence area
>    on the original contract.
>    - Yes, ATT created the drainage areas prior to removal and after
>    removal - I have photos.
>
> I have complete photo/video documentation of everything if needed.
>
> On Fri, Apr 29, 2022 at 10:31 AM Vincent Lim <vincent@haight-davis.com>
> wrote:
>
>> Hey Ms. Zeeman,
>>
>> I am emailing you with regards to getting some more information with
>> respect to the background of your property on 2740 Grove STreet NE in
>> Brookhaven.
>>
>> Do you have the specific dates/month of when the City of Brookhaven
>> performed their work by the area between the street and your home.
>>
>> Do you also have the dates of when AT&T performed work by your backyard
>> and when the possession of that section was passed between you and AT&T at
>> both times. Additionally, was it AT&T that dug the drainage trench
>> currently present, and if so when?
>>
>> Thanks for answering my questions
>>
>> Regards,
>> Vincent Lim, Project Engineer
>> Haight Davis & Associates, Inc.